rajul textile.

a comprehensive end-to-end guide

clothing manufacturing process

Eight phases carry a garment from first tech pack to packed and shipped. The timelines below are what we plan against.

Phase / Step Estimated Timeline Key Activities & Requirements Important Considerations
1 Mindset & Preparation Ongoing (3 months overall post-sampling) Commit to realistic timelines and an ethical manufacturing approach. Understand that various aspects (shipping, QC, sourcing) must align. First-time productions naturally take longer than subsequent ones. Producing ethically supports local communities and living wages.
2 Tech Packs & Quoting Initial Phase Submit a detailed ‘Tech Pack’ including measurements, desired fabrics, printing techniques, lining details, and reference images. Quotes provided are approximations for C.M.T (Cut, Make, Trim) only and do NOT include material costs. Complex designs increase costs.
3 Material Sourcing Prior to Sampling Identify desired fabrics and materials. Suppliers can assist with in-house or outsourced screen/digital printing. Custom dyes and printed fabrics often require Minimum Order Quantities (MOQs). Manufacturing textiles directly from a mill is an option for custom needs.
4 Patterns & Sampling 1 to 4 Weeks Tech packs are converted into paper drafting templates, then cut and sewn into initial samples. Provide a preferred sizing guide (US, UK, EU, etc.) for grading. Sample creation typically costs 4-5x the bulk production rate. Patterns and samples are charged separately.
5 Sample Review & Testing Client Dependent Review samples for fit, drape, and feel. Test durability by pulling seams and washing/drying 3-4 times according to care instructions. Communicate required changes using exact centimeter measurements, annotated photos, or physical notes on the garment. Fabric changes require restarting this phase.
6 Pre-Production 1 to 4 Weeks (Up to 2 months for custom textiles) Once ‘master samples’ are perfect, order all bulk fabrics, elastics (or framilon), and accessories (buttons, zippers, snaps, eyelets). Standard fabric/hardware delivery takes 1-2 weeks. Custom textiles from a mill can take up to 2 months. Custom hardware takes up to 4 weeks.
7 Bulk Production (CMT) 1 to 3 Months The mass Cut, Make, and Trim (CMT) production phase is executed based on the master sample. The exact timeframe depends on total quantity, design complexity, and the factory’s current production schedule.
8 Quality Control (QC) & Delivery During Production + 3 Days Post-Delivery Factory performs random Quality Control on 15-20% of pieces during bulk production. Client reviews final shipped order within 3 days of receipt. Errors caught during production are corrected immediately. Defective items identified by the client within 3 days will be repaired or replaced. Final items are pressed, packed, and shipped.
1 Mindset & Preparation Ongoing (3 months overall post-sampling)

Key Activities & Requirements

Commit to realistic timelines and an ethical manufacturing approach. Understand that various aspects (shipping, QC, sourcing) must align.

Important Considerations

First-time productions naturally take longer than subsequent ones. Producing ethically supports local communities and living wages.

2 Tech Packs & Quoting Initial Phase

Key Activities & Requirements

Submit a detailed ‘Tech Pack’ including measurements, desired fabrics, printing techniques, lining details, and reference images.

Important Considerations

Quotes provided are approximations for C.M.T (Cut, Make, Trim) only and do NOT include material costs. Complex designs increase costs.

3 Material Sourcing Prior to Sampling

Key Activities & Requirements

Identify desired fabrics and materials. Suppliers can assist with in-house or outsourced screen/digital printing.

Important Considerations

Custom dyes and printed fabrics often require Minimum Order Quantities (MOQs). Manufacturing textiles directly from a mill is an option for custom needs.

4 Patterns & Sampling 1 to 4 Weeks

Key Activities & Requirements

Tech packs are converted into paper drafting templates, then cut and sewn into initial samples. Provide a preferred sizing guide (US, UK, EU, etc.) for grading.

Important Considerations

Sample creation typically costs 4-5x the bulk production rate. Patterns and samples are charged separately.

5 Sample Review & Testing Client Dependent

Key Activities & Requirements

Review samples for fit, drape, and feel. Test durability by pulling seams and washing/drying 3-4 times according to care instructions.

Important Considerations

Communicate required changes using exact centimeter measurements, annotated photos, or physical notes on the garment. Fabric changes require restarting this phase.

6 Pre-Production 1 to 4 Weeks (Up to 2 months for custom textiles)

Key Activities & Requirements

Once ‘master samples’ are perfect, order all bulk fabrics, elastics (or framilon), and accessories (buttons, zippers, snaps, eyelets).

Important Considerations

Standard fabric/hardware delivery takes 1-2 weeks. Custom textiles from a mill can take up to 2 months. Custom hardware takes up to 4 weeks.

7 Bulk Production (CMT) 1 to 3 Months

Key Activities & Requirements

The mass Cut, Make, and Trim (CMT) production phase is executed based on the master sample.

Important Considerations

The exact timeframe depends on total quantity, design complexity, and the factory’s current production schedule.

8 Quality Control (QC) & Delivery During Production + 3 Days Post-Delivery

Key Activities & Requirements

Factory performs random Quality Control on 15-20% of pieces during bulk production. Client reviews final shipped order within 3 days of receipt.

Important Considerations

Errors caught during production are corrected immediately. Defective items identified by the client within 3 days will be repaired or replaced. Final items are pressed, packed, and shipped.